How Long Does a Bathroom Renovation Take? A Week-by-Week Plan
Short answer: A standard full bathroom renovation in Waterloo Region typically takes 2-3 weeks on site. Smaller jobs are faster, and larger ensuites take longer. Below is the week-by-week plan and the things that can add days.
For a typical full bathroom (about 5x8, about 40 sq ft), plan on 2-3 weeks of work on site. That is a full gut to the studs, new plumbing and electrical, a waterproofed tiled shower, and finishes.
That number is the time crews are working in your home. It does not include the planning before the job starts. Good planning is what keeps the on-site part on schedule.
Timeline by type of bathroom
Time depends mostly on how much is being torn out and how much tile is going in. Here is what to expect for common jobs in Kitchener, Waterloo, Cambridge, Guelph and nearby towns.
| Project | Typical timeline | Typical size |
|---|---|---|
| Powder room | 1 week | Up to 25 sq ft |
| Tub-to-shower conversion | 1-2 weeks | Tub space about 60x32, any bathroom |
| Full bathroom, Essential | 2-3 weeks | 5x8, about 40 sq ft |
| Full bathroom with walk-in shower | 2-3 weeks | 5x8, about 40 sq ft |
| Full bathroom, Signature | 3-4 weeks | 40-60 sq ft |
| Ensuite, Essential | 4-5 weeks | 60-110 sq ft |
| Ensuite, Signature | 5-6 weeks | 60-110 sq ft |
A tub-to-shower conversion is faster because the vanity, toilet and floor stay. A Signature job takes longer because of larger tile, custom glass, and more detail work.
Free on-site visit in Kitchener, Waterloo, Cambridge or Guelph. We measure, take photos and send you one clear fixed price.
Week-by-week plan for a full bathroom
This is how a standard full bathroom usually runs. Your exact schedule will be in your quote after the free on-site visit.
Before work starts: planning
This happens before the crew arrives, and it is where most delays are avoided.
- Book a free on-site visit. We measure and take photos.
- Get a fixed-price quote. Quotes are valid for 30 days.
- Choose your tile, vanity, toilet, faucets, shower valve trim and glass.
- Pay the 30% deposit and agree on a start date.
Have your choices made and your products ordered before demolition. Waiting on a vanity or a special tile is the number one reason a bathroom job stalls.
Week 1: demolition and rough-in
The old bathroom comes out down to the studs. We protect the path through your home, haul away debris, and check what is behind the walls and under the floor.
Next comes the rough-in. Licensed plumbers move or replace supply and drain lines and set the shower valve. Licensed electricians run wiring for the fan, lights and GFCI outlet. Any framing changes happen now, too.
If your city requires an inspection for the work, it is usually timed after rough-in and before the walls are closed up. Confirm what applies with your city building department.
Week 2: waterproofing and tile
Walls are closed up with new drywall. In the shower, we install Schluter Kerdi waterproofing. For a tiled shower, we then run a 24-hour water test before any tile goes on. This test is a built-in pause, so the schedule includes it.
Once the test passes, tile goes on the shower walls and the floor. Thinset and grout need time to set and cure, so tile work cannot be rushed without risking problems later.
Week 3 (if needed): finishing
The vanity, toilet, fan, vanity light, and fixtures go in. The glass door or panel is installed after the walls are done. Then paint, caulking, touch-ups, and a final clean.
Smaller bathrooms may finish earlier in the range. Bigger rooms or more detailed tile layouts use the full range.
What can make it take longer
- Surprises behind the walls. Older homes in Kitchener, Cambridge and Guelph can have rotted subfloor, old plumbing, or past water damage. Fixing it adds time.
- Late or backordered products. Custom glass, special tile, and some vanities can take a while to arrive. Order early.
- Changes after the job starts. Switching tile, adding a niche, or moving a drain after demolition resets parts of the plan.
- Layout changes. Moving the toilet, shower or vanity means more plumbing work and may need a permit. Read our bathroom renovation permit guide for the general rules.
- Permit or inspection timing. When a permit is needed, your city's schedule can affect the start date or the pause between stages.
- Bigger rooms. More area means more tile, more fixtures, and more steps. See our ensuite renovation guide for what drives larger jobs.
What Nova includes in a full bathroom
Our Essential full bathroom package starts at $18,000 + HST ($20,340 with HST). The typical market range in the region is $15K-28K. The package includes:
Full gut to studs. Shower: acrylic base 60x32 with sliding glass door, OR alcove tub. Shower walls tiled to 7 ft on Kerdi waterproofing. Vanity, toilet, floor tile, fan, vanity light, GFCI, drywall, paint.
The price is fixed and agreed before work starts. Plumbing and electrical are done by licensed tradespeople, and the work comes with a 2-year workmanship warranty. For a deeper look at costs, see Bathroom Renovation Cost Kitchener-Waterloo.
Common mistakes that add time
- Starting before you choose finishes. You do not want to pick tile while the crew waits.
- Assuming a short job means no planning. Even a tub-to-shower conversion needs the glass, valve and tile chosen in advance. See Tub to Shower Conversion Cost for what is included.
- Skipping the water test to save a day. A leak in a finished shower costs far more time than the test does.
- Having only one bathroom. If this is your only bathroom, plan for where your household will wash. Ask about this before the start date.
- Choosing a contractor on speed alone. A very short promise can mean skipped steps. Our 10 questions for choosing a contractor will help you compare.
How to get an accurate timeline for your bathroom
Every bathroom is different, so the best answer comes from seeing it. Here is how it works with Nova:
- Call (226) 507-0723 or book through the site.
- We visit your home for free. We measure, take photos, and look at access, plumbing and the age of the house.
- You get a detailed, fixed-price quote with the scope and the expected timeline.
- You choose your finishes and we agree on a start date.
We serve Kitchener, Waterloo, Cambridge, Guelph, Elmira, St. Jacobs, New Hamburg, Baden, Ayr, Wellesley, Breslau, Fergus and Elora.
Free on-site visit in Kitchener, Waterloo, Cambridge or Guelph. We measure, take photos and send you one clear fixed price.
Frequently asked questions
How long does a full bathroom renovation take?
A standard full bathroom usually takes 2-3 weeks on site. Larger or more detailed bathrooms take longer.
How long does a tub-to-shower conversion take?
Most conversions take 1-2 weeks. It is faster than a full renovation because the vanity, toilet and floor stay in place.
Can I use my bathroom during the renovation?
No. The room is torn out and the plumbing is shut off during the work. If it is your only bathroom, plan ahead for where you will wash and use the toilet.
Why does tile take so long?
Tile needs a waterproofed base, setting time, and grout curing. In a tiled shower, we also run a 24-hour water test before tile goes on. These steps protect your home from leaks.
Do I need a permit, and will it add time?
Moving plumbing or changing structure usually needs a permit. Same-layout work often does not. Confirm with your city building department, because their timing can affect your schedule.
How long does an ensuite renovation take?
An Essential ensuite takes about 4-5 weeks, and a Signature ensuite about 5-6 weeks. These rooms are larger and have more fixtures and tile.